A parts manufacturer cut scrap by 22% by catching drift on the shift it starts.
A parts manufacturer recorded inspections on paper and found quality problems only after whole batches were made. We built a production and quality system that catches drift as it happens, and scrap fell from 4.1% of parts to 3.2%.
Parts scrapped
Before4.1%
With Harnet3.2%
Before and after
The numbers before and after.
-
Parts scrapped
−22%
-
Time until a drifting machine is noticed
−80%
-
Inspection results typed up by hand
- Client
- Parts manufacturer, 3 production lines
- First working version
- 72 hours
- Live in
- 4 weeks, line by line
- Measured over
- Four months after launch
The situation
What the firm was dealing with.
Operators wrote inspection results on paper sheets. Quality engineers typed them into spreadsheets at the end of the week, long after the parts had shipped or been scrapped.
When a machine drifted out of tolerance, nobody saw it until a full batch failed inspection. The same problems came back because no one could see the pattern across shifts and machines.
Before Harnet
- Inspections recorded on paper
- Quality data typed up once a week
- 4.1% of parts scrapped
- No view across machines and shifts
What we built
One system, built around how the team works.
- 01
Inspections at the machine
Operators record measurements on a tablet. A reading outside tolerance alerts the shift lead straight away.
- 02
Production tracking
Follows each job through every machine and shift, with its materials, settings and inspection results.
- 03
Quality trends
Shows readings by machine, part and shift, so engineers see drift before it turns into scrap.
- 04
Problem log
Keeps every problem, its cause and its fix in one place, so the next shift does not repeat it.
Checks and approvals
What it does on its own, and what stays with people.
The system handles the routine work. Anything that must be exact is checked by code, and anything hard to undo waits for a person.
- Tolerances come from the engineering drawings and only quality engineers can change them.
- Alerts go to the shift lead. The system never stops a machine on its own.
- Every reading is stored with the operator, the machine and the time.
How the project ran
From first conversation to launch.
The team was using a first version within 72 hours. It then ran beside the team on real work until the results matched, and every correction became a new check.
- Day 1
Walked the floor with operators and quality engineers.
- Hour 72
First working version: tablet inspections on one production line.
- Week 2
Added production tracking and quality trends on the first line.
- Week 3
Rolled out to the second and third lines and added the problem log.
- Week 4
Retired the paper inspection sheets.
Results
What changed.
Measured over four months after launch, against the baseline we recorded before the project started.
- 22%less scrap, from 4.1% of parts to 3.2%
- Same shiftdrift is caught on the shift it starts
- 0inspection sheets typed up by hand
- Drift is caught before a batch fails
- Engineers see patterns across machines and shifts
- Fixes are recorded, so problems do not come back
| Area | Before | After |
|---|---|---|
| Inspections | Paper sheets | Recorded at the machine |
| Quality data | Typed up weekly | Live, with alerts |
| Scrap | 4.1% of parts | 3.2% |
Does your firm have a process like this one?
Book a callMore case studies
Other firms we built for.
77%
less spent on the tools it replaced
An investment firm replaced four vendor tools with one platform it owns, for under a quarter of the cost.
Read the case study+17%
more new matters, same team
A law firm automated client intake and now opens 17% more matters with the same team.
Read the case study21%
shorter engagements